Project Description:
MANSFIELD- RECONSTRUCTION OF ROUTE 106 (CHAUNCY STREET) INCLUDES RAILROAD BRIDGE M-03-019
The proposed project consists of the rehabilitation of the Chauncy Street underpass structure, its' pumping facility, and the storm water drainage and discharge system in Mansfield. The underpass has experienced flooding and ground water seepage onto the roadway. During cold temperatures, the seepage freezes on the roadway and causes hazardous conditions. This project will mitigate these problems.
Location:
  • Town of Mansfield
  • Resident Engineer: Thomas Kewriga
    Construction Contract Value: $5,605,448.63
    Construction Bid Price: $4,313,313.31
    Initial Construction Estimate: $4,836,960.50
    District: District 5

    Contracts (3) Progress
    # 34047 -- Design -- Bridge Rehab/Recon/New Const
    Preparation of contract documents necessary to implement the repairs to the underpass structure and pump house. Final
    # 51302 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 55284 -- Construction Contract
    Mansfield - Reconstruction of Bridge (M-03-019) Rte 109 (cfhauncy Street) under MBTA Railroad Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/18/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/29/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 11/24/2003
    Project Status Advertised 04/26/2008
    Project Management
    100% Design 100% Package Received 08/15/2007
    100% Design 100% Package Comments to DE 11/01/2007
    25% Design 25% Package Received 09/15/2004
    25% Design 25% Package Received 09/27/2006
    25% Design 25% Package Comments to DE 09/30/2005
    25% Design 25% Package Comments to DE 12/20/2006
    25% Design Design Public Hearing 12/14/2006
    75% Design 75% Package Received 03/19/2007
    75% Design 75% Package Comments to DE 06/08/2007
    Final Design PS&E Received 12/14/2007
    Final Design PS&E Received 04/22/2008
    Final Design PS&E to FAPRO 12/20/2007
    Final Design PS&E to FAPRO 04/23/2008
    Consultant Contract Process Scope to DE 06/19/2003
    Consultant Contract Process NTP Issued 12/01/2003
    Consultant Contract Process Workhours Approved 09/25/2003