Project Description:
DISTRICT 4- INSTALLATION OF REFLECTORIZED REFERENCE LOCATION SIGNS ON VARIOUS ROUTES
This project will provide new reference location signs (mileposts) on various non-controlled access Federal Primary and State numbered routes within District 4.
Location:
Resident Engineer: Pasquale Mele
Construction Contract Value: $496,350.06
Construction Bid Price: $383,006.06
Initial Construction Estimate: $611,950.00
District: District 4
Current Status: Pre-installation GPS survey is almost complete. Signs are now being installed at various locations. (as of 06/25/2007)

Contracts (1) Progress
# 43816 -- Construction Contract
Installation of Reference Location Markers on various secondary state highways within District 4 Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/13/2006
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Pre-installation GPS survey is almost complete. Signs are now being installed at various locations.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/24/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Status Advertised 09/17/2005
    Project Management
    100% Design 100% Package Received 09/07/2005
    Final Design PS&E Received 09/12/2005
    Final Design PS&E to FAPRO 09/12/2005