TISBURY- RESURFACING AND RELATED WORK ON FRANKLIN STREET
Location:
  • Town of Tisbury
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $437,995.00
    Construction Bid Price: $390,632.00
    Initial Construction Estimate: $343,140.00
    District: District 5

    Contracts (1) Progress
    # 37991 -- Construction Contract
    Work consist of full width Hot Mix Asphalt Paving with a leveling course and a 1.5 inch wearing surface, including pavement markings, sign upgrade and drainage improvements. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/30/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/05/2003
    Project Review Committee PRC Tabled 11/18/2003
    Project Review Committee PRC Approved 12/03/2003
    Project Review Committee Letter 01/09/2004
    Project Status Advertised 09/25/2004
    Project Management
    25% Design 25% Package Received 12/16/2003
    Final Design PS&E Received 09/14/2004
    Final Design PS&E to FAPRO 09/14/2004