DENNIS- RECONSTRUCTION OF SWAN RIVER ROAD, ROUTE 134 TO LOWER COUNTY ROAD
The project consists of the reconstruction of Swan River Road from the intersection with Route 28 near Route 134 to the intersection with Lower County Road. The project involves minor widening and the installation of curbing, sidewalks, wheelchair ramps, signs and pavement markings. Drainage improvements will be provided, some privately owned features within the town right-of way will be removed, and utility poles will be relocated.
Location:
  • Town of Dennis
  • Resident Engineer: Thomas Ockerbloom
    Construction Contract Value: $2,822,980.00
    Construction Bid Price: $2,395,527.75
    Initial Construction Estimate: $2,098,730.50
    District: District 5

    Contracts (1) Progress
    # 53076 -- Construction Contract
    Dennis - Roadway Reconstruction and Related Work on Sections of Swan River Road and Lower County Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/28/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/10/2003
    Project Review Committee PRC Tabled 11/18/2003
    Project Review Committee PRC Approved 12/03/2003
    Project Review Committee Letter 01/09/2004
    Project Status Advertised 08/12/2006
    Project Management
    100% Design 100% Package Received 03/10/2006
    100% Design 100% Package Comments to DE 05/19/2006
    25% Design 25% Package Received 12/09/2004
    25% Design 25% Package Received 02/15/2005
    25% Design 25% Package Comments to DE 06/16/2005
    25% Design 25% Package Approved 09/20/2005
    25% Design Design Public Hearing 04/21/2005
    25% Design 25% Plans Complete 08/05/2005
    75% Design 75% Package Received 10/28/2005
    75% Design 75% Package Comments to DE 01/31/2006
    75% Design 75% Plans Complete 01/31/2006
    Final Design PS&E Received 07/07/2006
    Final Design PS&E to FAPRO 07/25/2006