Project Description: |
BARNSTABLE- ROUNDABOUT CONSTRUCTION AT INTERSECTION OF ROUTE 149 & ROUTE 6 (EB) EXIT RAMP
Work on this project consists of installing a roundabout at the intersection of the eastbound exit ramp of Route 6 and Route 149. The work will include installing sidewalks, guard rail, bike paths and crosswalks at the intersection. The work will also include increasing the length of the deceleration lanes on Route 6 eastbound and westbound.
|
Location: |
|
Resident Engineer: | Michael King |
Construction Contract Value: | $1,500,177.00 |
Construction Bid Price: | $1,290,390.82 |
Initial Construction Estimate: | $1,586,805.00 |
District: | District 5 |
|
Bridges |
|
|
|
|