Project Description:
NANTUCKET- BIKE PATH CONSTRUCTION ON BARTLETT ROAD
This proposed project involves the construction of a bike path adjacent to Bartlett Road between Mizzenmast Lane and Raceway Drive in the Town of Nantucket. The proposed bike path will be approximately 1,664 feet in length and will connect to an existing bike path that terminates east of Raceway Drive and west of Mizzenmast Lane.
Location:
  • Town of Nantucket
  • Resident Engineer: Michael McGovern
    Construction Contract Value: $321,725.79
    Construction Bid Price: $249,956.90
    Initial Construction Estimate: $289,400.00
    District: District 5

    Contracts (1) Progress
    # 53679 -- Construction Contract
    Nantucket - Construction of Bartlett Road (Bicycle Path) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/28/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/10/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Review Committee Letter 05/04/2003
    Project Status Advertised 09/23/2006
    Project Management
    100% Design 100% Package Received 05/30/2006
    100% Design 100% Package Comments to DE 07/14/2006
    25% Design 25% Package Received 04/01/2005
    25% Design 25% Package Comments to DE 08/17/2005
    25% Design Design Public Hearing 10/06/2005
    75% Design 75% Package Received 12/10/2005
    75% Design 75% Package Comments to DE 03/22/2006
    Final Design PS&E Received 08/07/2006
    Final Design PS&E to FAPRO 09/12/2006