Project Description:
BARNSTABLE- SIGNAL & INTERSECTION IMPROVEMENTS ON ROUTE 28 @ 3 LOCATIONS: LUMBERT MILLS ROAD, SOUTH COUNTY ROAD AND ROUTE 149
This project involves the installation of new traffic signal systems at 3 locations on Route 28 and associated geometric improvements.
Location:
  • Town of Barnstable
  • Resident Engineer: Joseph Gedraitis
    Construction Contract Value: $2,436,896.00
    Construction Bid Price: $1,981,360.25
    Initial Construction Estimate: $2,307,305.00
    District: District 5

    Contracts (2) Progress
    # 54138 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 59674 -- Construction Contract
    Intersection Improvements and Related Work on Route 28 (Falmouth Road) at 3 Locations. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/06/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/10/2003
    Project Review Committee PRC Tabled 11/18/2003
    Project Review Committee PRC Approved 12/03/2003
    Project Review Committee Letter 01/09/2004
    Project Status Initiated 09/23/2005
    Project Status Advertised 06/27/2009
    Project Management
    100% Design 100% Package Received 03/31/2009
    100% Design 100% Package Comments to DE 05/14/2009
    25% Design 25% Package Received 05/12/2008
    25% Design 25% Package Comments to DE 06/20/2008
    25% Design Design Public Hearing 08/13/2008
    75% Design 75% Package Received 11/25/2008
    75% Design 75% Package Comments to DE 01/22/2009
    Final Design PS&E Received 06/15/2009
    Final Design PS&E to FAPRO 06/24/2009
    Consultant Contract Process NTP Issued 09/14/2005