Project Description:
BECKET- CONSTRUCTION OF A CHEMICAL STORAGE FACILITY ON ROUTE 8
Construction of a 44'x88' salt storage facility in the Town of Becket.
Location:
  • Town of Becket
  • Resident Engineer: Kevin Mahoney
    Construction Contract Value: $195,900.00
    Construction Bid Price: $183,000.00
    Initial Construction Estimate: $184,455.00
    District: District 1
    Current Status: Project is substantially complete. (as of 12/19/2005)

    Contracts (1) Progress
    # 37485 -- Construction Contract
    604107 - Construction of Chemical Storage Shed Facility Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/21/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project is substantially complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/07/2003
    Project Review Committee PRC Approved 11/18/2003
    Project Status Advertised 09/11/2004
    Project Management
    Final Design PS&E to FAPRO 06/08/2004