Project Description: |
BECKET- CONSTRUCTION OF A CHEMICAL STORAGE FACILITY ON ROUTE 8
Construction of a 44'x88' salt storage facility in the Town of Becket.
|
Location: |
|
Resident Engineer: | Kevin Mahoney |
Construction Contract Value: | $195,900.00 |
Construction Bid Price: | $183,000.00 |
Initial Construction Estimate: | $184,455.00 |
District: | District 1 |
Current Status: | Project is substantially complete. (as of 12/19/2005) |
|
Bridges |
|
|
|
|