ASHBURNHAM- RECLAMATION & RELATED WORK ON ROUTE 101 (ASHBY ROAD), FROM STOWELL ROAD TO ROUTE 119
This Footprint Road project begins at the intersection of Route 101 with Stowell Road and proceeds northerly 3.0 miles to the intersection with Route 119 (Rindge State Road).
Location:
  • Town of Ashburnham
  • Resident Engineer: Lisa Spezzaferro-Pelleti
    Construction Contract Value: $1,732,129.00
    Construction Bid Price: $1,528,418.00
    Initial Construction Estimate: $1,619,200.00
    District: District 3

    Contracts (1) Progress
    # 69355 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 101 (Ashby Road). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/23/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/07/2003
    Project Review Committee PRC Tabled 12/03/2003
    Project Review Committee PRC Tabled 06/22/2004
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 02/01/2006
    Project Status Initiated 11/30/2005
    Project Status Advertised 06/11/2011
    Project Management
    100% Design 100% Package Received 05/27/2011
    25% Design 25% Package Received 02/18/2010
    75% Design 75% Package Received 04/13/2011
    75% Design 75% Package Comments to DE 03/26/2010
    75% Design 75% Package Comments to DE 05/04/2011
    Final Design PS&E Received 05/27/2011
    Final Design PS&E to FAPRO 06/01/2011