NORTHBOROUGH- SIGNAL IMPROVEMENTS ON ROUTE 20 @ 3 INTERSECTIONS: CHURCH STREET, SOUTH STREET, HUDSON STREET
The project location is Route 20, from approximately 1000 feet west of Church Street easterly to a location 600 feet east of Hudson Street for a distance of approximately 0.5 miles. A signal will be installed at the intersection of Route 20 and Hudson Street and the equipment at Church Street and South Street will be upgraded. The three signals will be interconnected.
Location:
  • Town of Northborough
  • Resident Engineer: Angela Padavano
    Construction Contract Value: $2,930,413.60
    Construction Bid Price: $2,527,105.69
    Initial Construction Estimate: $2,809,282.80
    District: District 3

    Contracts (4) Progress
    # 57728 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70722 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Traffic Signals) on a Section of Route 20 at Church, South and Hudson Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/28/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/07/2003
    Project Review Committee PRC Tabled 11/18/2003
    Project Review Committee PRC Approved 12/03/2003
    Project Review Committee Letter 01/08/2004
    Project Status Advertised 08/27/2011
    Project Management
    100% Design 100% Package Received 02/03/2011
    100% Design 100% Package Comments to DE 03/21/2011
    25% Design 25% Package Received 01/16/2009
    25% Design 25% Package Comments to DE 06/12/2009
    25% Design Design Public Hearing 09/10/2009
    75% Design 75% Package Received 02/24/2010
    75% Design 75% Package Comments to DE 07/28/2010
    Final Design PS&E Received 05/26/2011
    Final Design PS&E Received 07/28/2011
    Final Design PS&E to FAPRO 08/17/2011