Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BERNARDSTON- GREENFIELD- MICROSURFACING PAVEMENT PRESERVATION AND RELATED REPAIRS, ROUTE I-91
Location:
  • Town of Bernardston
  • Town of Greenfield
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Albert Li
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: This project has been advertised for construction bids. (as of 05/01/2004 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/07/2003
    Project Review Committee PRC Approved 12/03/2003
    Project Review Committee Letter 12/30/2003
    Project Status Advertised 05/01/2004
    Project Management
    Final Design PS&E Received 03/29/2004
    Final Design PS&E to FAPRO 04/07/2004