Project Description:
DARTMOUTH- STORAGE BUILDING CONSTRUCTION (FAUNCE CORNER DEPOT)
Work on this project consists of construction of a storage building.
Location:
  • Town of Dartmouth
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2050/2051
    Project Manager: Edmond Libsch
    Estimated Total Contract Cost: $2,000,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: 100% Package Comments to DE (as of 10/08/2014 )

    Contracts (1) Progress
    # 64302 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/25/2003
    Project Review Committee PRC Approved 06/22/2004
    Project Review Committee Letter 08/10/2004
    Project Management
    100% Design 100% Package Received 08/28/2014
    100% Design 100% Package Comments to DE 10/08/2014