Project Description:
BOURNE- PLYMOUTH- WAREHAM- TRAFFIC SIGN REPLACEMENT AND SAFETY IMPROVEMENTS, ROUTE 25
Replacement and update of all overhead and ground mounted sign panels, exit gore, warning, regulatory and route marker sign panels on Route 25 from Route 6/28 interchange in Wareham to the Route 6/28 interchange in Bourne.
Location:
  • Town of Bourne
  • Town of Plymouth
  • Town of Wareham
  • Resident Engineer: Kenneth White
    Construction Contract Value: $287,464.77
    Construction Bid Price: $242,215.37
    Initial Construction Estimate: $287,605.78
    District: District 5

    Contracts (1) Progress
    # 43799 -- Construction Contract
    Replacement of guide and traffic signs on State Route 25 between U.S. 6 in Bourne and I-195 in Wareham Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/15/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/10/2003
    Project Review Committee PRC Approved 06/22/2004
    Project Review Committee Letter 08/10/2004
    Project Status Advertised 08/13/2005
    Project Management
    Final Design PS&E Received 08/09/2005
    Final Design PS&E to FAPRO 08/09/2005