SANDISFIELD- BRIDGE REHABILITATION, S-03-023, NORFOLK ROAD OVER SANDY BROOK
This bridge replacement project carries Norfolk Road over Sandy Brook. Work also includes reconstruction of bridge approaches, highway guardrail, pavement marking, loam borrow and seeding, and other incidental work. This bridge will be closed during construction and a detour will be posted.
Location:
  • Town of Sandisfield
  • Resident Engineer: Joseph Mastroianni
    Construction Contract Value: $1,133,448.27
    Construction Bid Price: $933,529.21
    Initial Construction Estimate: $736,092.90
    District: District 1

    Contracts (2) Progress
    # 56251 -- Construction Contract
    Sandisfield - Bridge Replacement (S-03-023), Norfolk Road over Sandy Brook, PF #604139 Completed
    # 59588 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/10/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/15/2003
    Project Review Committee PRC Approved 06/22/2004
    Project Status Advertised 06/21/2008
    Project Management
    100% Design 100% Package Received 07/11/2007
    100% Design 100% Package Comments to DE 09/07/2007
    25% Design 25% Package Received 09/06/2005
    25% Design 25% Package Comments to DE 11/17/2005
    25% Design Design Public Hearing 01/31/2006
    75% Design 75% Package Received 01/12/2007
    75% Design 75% Package Comments to DE 05/30/2007
    Final Design PS&E Received 12/26/2007
    Final Design PS&E to FAPRO 12/27/2007
    Consultant Contract Process NTP Issued 02/10/2005