Project Description:
DISTRICT 4- GUARDRAIL END UPGRADES ON INTERSTATE HIGHWAYS
This work consists of furnishing, labor equipment and materials that are necessary to remove and replace existing "buried end" guardrail end treatments.
Location:
Resident Engineer: Scott Venuti
Construction Contract Value: $1,813,295.96
Construction Bid Price: $1,353,723.60
Initial Construction Estimate: $1,426,300.00
District: District 4
Current Status: The contractor worked last on 6/16/2006 on this project . The ending date was 6/30/2006. It is now substantially complete and ready to be finaled. (as of 06/05/2006)

Contracts (1) Progress
# 34628 -- Construction Contract
Guardrail End Upgrades. (2 Separate Contracts) Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/19/2004
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The contractor worked last on 6/16/2006 on this project . The ending date was 6/30/2006. It is now substantially complete and ready to be finaled.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/29/2003
    Project Status Advertised 02/28/2004
    Project Management
    25% Design 25% Package Received 04/16/2004
    25% Design 25% Package Comments to DE 04/16/2004
    25% Design 25% Package Approved 04/16/2004
    25% Design Design Public Hearing 04/16/2004
    25% Design 25% Plans Complete 04/16/2004