Project Description:
SOUTHWICK- RECONSTRUCTION OF ROUTE 10/202 (COLLEGE HIGHWAY - CENTER SECTION) FROM TANNERY ROAD TO 0.2 MILES SOUTH OF ROUTE 57
The project begins at Tannery Road and proceeds southerly ending at 445 College Highway Guiel’s Auto Body. The drainage system will include a drainage trunk line that will run along Tannery Road approximately 1377 feet ending where Slab Brook meets Tannery Road. The total length of the project is approximately 1.5 miles. The work to be done under this contract includes full depth reconstruction, cold planing, resurfacing, box widening with the addition of an exclusive center turning lane, concrete sidewalks and concrete wheelchair ramps, traffic signal reconstruction at two intersections, the extension of a culvert, drainage improvements and ornamental street lighting.
Location:
  • Town of Southwick
  • Resident Engineer: Sean Sullivan
    Construction Contract Value: $5,500,440.58
    Construction Bid Price: $4,842,105.07
    Initial Construction Estimate: $4,902,648.50
    District: District 2

    Contracts (1) Progress
    # 68208 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Routes 10 & 202 (College Highway). (RE-ADVERTISED) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/06/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/12/2004
    Project Review Committee PRC Approved 06/22/2004
    Project Review Committee PRC Approved 09/14/2006
    Project Review Committee Letter 07/19/2004
    Project Status Initiated 09/01/2006
    Project Status Advertised 09/18/2010
    Project Management
    100% Design 100% Package Received 07/16/2010
    25% Design 25% Package Received 11/22/2006
    25% Design 25% Package Comments to DE 08/02/2007
    25% Design Design Public Hearing 01/26/2006
    25% Design 25% Plans Complete 04/27/2007
    75% Design 75% Package Received 03/30/2010
    Final Design PS&E Received 08/31/2010
    Final Design PS&E to FAPRO 09/08/2010