NORTHBRIDGE- BRIDGE REPLACEMENT, N-21-004, DOUGLAS ROAD OVER THE MUMFORD RIVER
The proposed project consists of replacement of the existing two span masonry arch bridge, built in 1857 and reconstructed in 1923, carrying Douglas Road over the Mumford River. The proposed replacement bridge consists of a concrete single span bridge with features to complement the architectural aesthetics of the surrounding historic district. Two way traffic and pedestrian access will be maintained throughout construction through the use of a temporary bridge. Also included is the necessary roadway reconstruction, utility relocation, drainage and other incidental work.
Location:
  • Town of Northbridge
  • Resident Engineer: Scott Fitzgerald
    Construction Contract Value: $4,870,461.00
    Construction Bid Price: $4,197,358.00
    Initial Construction Estimate: $4,336,448.00
    District: District 3

    Contracts (7) Progress
    # 43180 -- Design -- Bridge Rehab/Recon/New Const
    Preliminary and final highway and structural design for the replacement of two span masonry arch structure in Northbridge. Final
    # 51303 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 54837 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final
    # 64300 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68382 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 72135 -- Construction Contract
    Bridge Replacement Br. No. N-21-004 (Concrete) Douglas Road over the Mumford River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/08/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/20/2004
    Project Review Committee PRC Approved 06/22/2004
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 07/19/2004
    Project Review Committee Letter 12/29/2005
    Project Status Advertised 12/10/2011
    Project Management
    25% Design 25% Package Received 09/28/2008
    25% Design 25% Package Received 03/03/2010
    25% Design 25% Package Received 09/17/2010
    25% Design 25% Package Comments to DE 05/21/2009
    25% Design 25% Package Comments to DE 04/21/2010
    25% Design 25% Package Comments to DE 11/10/2010
    25% Design Design Public Hearing 05/05/2010
    75% Design 75% Package Received 02/15/2011
    75% Design 75% Package Comments to DE 04/21/2011
    Final Design PS&E Received 07/12/2011
    Final Design PS&E to FAPRO 12/07/2011
    Consultant Contract Process Scope to DE 01/06/2006
    Consultant Contract Process NTP Issued 10/03/2007
    Consultant Contract Process Workhours Approved 04/25/2007