Project Description:
NORTHBRIDGE- BRIDGE PRESERVATION, N-21-014, ROUTE 146 (NB) OVER MAIN STREET
Bridge deck replacement for Bridge No. N-21-14.
Location:
  • Town of Northbridge
  • Design Responsibility: Consultant
    Right of Way Responsibility: Other
    Project Manager: John Gendall
    Estimated Total Contract Cost: $1,127,451.74
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • N21014 
    See the Milestone Details tab for additional Project information