CHESHIRE- BRIDGE REPLACEMENT, C-10-007, HARBOR ROAD OVER HOOSIC RIVER
The existing bridge will be replaced with a single span Pratt Pony prefabricated steel truss founded on new concrete abutments.
Location:
  • Town of Cheshire
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Project Manager: Albert Miller
    Estimated Total Contract Cost: $1,477,472.53
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • C10007 
    See the Milestone Details tab for additional Project information