Project Description:
TOWNSEND- BRIDGE REPLACEMENT, T-07-011, VINTON POND ROAD OVER PEARL HILL BROOK
The project limits for the Viton Pond Road bridge project are from High Meadow Road to DiBendedetto Drive and includes work on Wellesley Street from South Avenue to the Weston High School. The work also includes a new traffic signal system, channelization, new curbing and sidewalks. A design exception may be required for the proposed shoulder width.
Location:
  • Town of Townsend
  • Resident Engineer: Frederick Stacy
    Construction Contract Value: $706,181.26
    Construction Bid Price: $635,113.50
    Initial Construction Estimate: $788,955.50
    District: District 3

    Contracts (1) Progress
    # 56876 -- Construction Contract
    Townsend - Bridge Replacment (T-07-011) Vinton Pond Road over Pearl Hill Brook Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/31/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/28/2004
    Project Review Committee PRC Tabled 06/22/2004
    Project Review Committee PRC Approved 04/21/2005
    Project Status Advertised 07/12/2008
    Project Management
    100% Design 100% Package Received 01/03/2006
    100% Design 100% Package Comments to DE 03/22/2006
    25% Design 25% Package Received 10/15/2004
    25% Design 25% Package Comments to DE 01/05/2005
    25% Design Design Public Hearing 01/17/2007
    75% Design 75% Package Received 06/20/2005
    75% Design 75% Package Comments to DE 08/23/2005
    Final Design PS&E Received 03/11/2008
    Final Design PS&E Received 05/06/2008
    Final Design PS&E Received 05/13/2008
    Final Design PS&E Received 05/23/2008
    Final Design PS&E to FAPRO 03/12/2008
    Final Design PS&E to FAPRO 05/07/2008
    Final Design PS&E to FAPRO 05/15/2008
    Final Design PS&E to FAPRO 05/27/2008
    Consultant Contract Process Scope to DE 03/08/2004
    Consultant Contract Process NTP Issued 04/30/2004
    Consultant Contract Process Workhours Approved 04/20/2004