Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- BRIDGE REPLACEMENT, B-16-016, NORTH WASHINGTON STREET OVER THE BOSTON INNER HARBOR
The North Washington Street Bridge is a historic structure constructed in 1898. The bridge consists of 10 approach spans and a swing span, which is not operational. The bridge is structurally deficient and is posted for restricted loads. There have been extensive emergency repairs done to the bridge in the past few years. Currently the two center lanes on the swing span are closed due to steel deterioration. The City of Boston proposes to replace the bridge. On the approach spans this replacement will include replacement of the existing granite/concrete bridge piers with reinforced concrete V piers and continuous trapezoidal steel box girders. Proposed deck will provide for increased bicycle and pedestrian accommodations between Kearney Square and Rutherford Ave.
Location:
  • City of Boston
  • Construction Begins: Summer 2018
    Resident Engineer: Sardar Jajan
    Construction Bid Price: $176,777,388.50
    District: District 6

    Contracts (5) Progress
    # 102269 -- Construction Contract
    Bridge Replacement Br. No. B-16-016 (Steel) North Washington Street over the Boston Inner Harbor. 93% Complete
    # 77867 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 80655 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering

    Bridges

    Contract Dates
    Notice to Proceed: 08/08/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/18/2004
    Project Review Committee PRC Approved 06/22/2004
    Project Status Advertised 09/16/2017
    Project Management
    100% Design 100% Package Received 04/04/2017
    100% Design 100% Package Comments to DE 05/26/2017
    25% Design 25% Package Received 01/13/2015
    25% Design 25% Plans Complete 03/06/2015
    75% Design 75% Package Received 08/19/2016
    Final Design PS&E Received 01/25/2018
    Final Design PS&E Received - Resub 2 01/29/2018