Project Description:
ROYALSTON- BRIDGE REPLACEMENT, R-12-004, NORTHEAST FITZWILLIAM ROAD OVER THE LAWRENCE BROOK
This bridge replacement project carries Northeast Fitzwilliam Road over Lawrence Brook. Work also includes reconstruction of bridge approaches, highway guardrail, pavement marking, loam borrow and seeding, and other incidental work. This bridge will be closed during construction and a detour will be posted.
Location:
  • Town of Royalston
  • Resident Engineer: Matthew Minihan
    Construction Contract Value: $1,176,755.87
    Construction Bid Price: $1,055,638.00
    Initial Construction Estimate: $1,408,738.00
    District: District 2

    Contracts (5) Progress
    # 30274 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 57463 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 64302 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64307 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 75584 -- Construction Contract
    Bridge Replacement (R-12-004) (Precast Concrete Arch) - Northeast Fitzwilliam Road over the Lawrence Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/19/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/24/2004
    Project Review Committee PRC Approved 06/22/2004
    Project Review Committee Letter 07/19/2004
    Project Status Advertised 09/15/2012
    Project Management
    100% Design 100% Package Received 08/13/2012
    25% Design 25% Package Received 11/21/2006
    25% Design 25% Package Comments to DE 05/14/2012
    25% Design Design Public Hearing 02/28/2008
    75% Design 75% Package Received 08/19/2008
    75% Design 75% Package Received 03/12/2012
    75% Design 75% Package Comments to DE 10/10/2008
    75% Design 75% Package Comments to DE 04/20/2012
    Final Design PS&E Received 09/12/2012
    Final Design PS&E to FAPRO 09/12/2012
    Consultant Contract Process NTP Issued 06/23/2005