Project Description:
DISTRICT 5- REFURBISHMENT OF CRASH CUSHION DEVICES (HYDROCELLS) AT STATE HIGHWAY LOCATIONS
This contract provides for replacing or refurbishing hydrocell crash cushions at various state highway locations in District 5, which have been struck and damaged by an unidentified or uninsured motorist and MassHighway has no recourse under the accident recovery process.
Location:
Resident Engineer: Stephen Soares
Construction Contract Value: $311,824.00
Construction Bid Price: $132,519.00
Initial Construction Estimate: $172,660.00
District: District 5

Contracts (1) Progress
# 36396 -- Construction Contract
Refurbishment of Crash Cushions (Hydrocells) in District 5. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/09/2004
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/05/2004
    Project Review Committee PRC Approved 06/22/2004
    Project Review Committee Letter 08/10/2004
    Project Status Advertised 07/31/2004
    Project Management
    Final Design PS&E Received 07/21/2004
    Final Design PS&E to FAPRO 07/21/2004