Project Description:
BERNARDSTON- BRIDGE REPLACEMENT, B-10-004, U.S. ROUTE 5 (BRATTLEBORO ROAD) OVER SHATTUCK BROOK
The work to be done on this project includes the replacement of a state-owned bridge on US Route 5 over Shattuck Brook. The bridge is located between Couchbrook (Haigis) Road and Keets Brook Road (at approximate mile marker 53.5), a distance of approximately 5,000 feet from the Vermont state border.
Location:
  • Town of Bernardston
  • Construction Begins: Summer 2020
    Resident Engineer: Victor LaMountain
    Construction Bid Price: $1,941,334.50
    District: District 2

    Contracts (5) Progress
    # 101634 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide and bridge projects, for the purpose of maintaining Final
    # 111227 -- Construction Contract
    Bridge Replacement Br. No. B-10-004 (Concrete) Brattleboro Road (Route 5) over Shattuck Brook Completed
    # 57735 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 58594 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64324 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/27/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/22/2004
    Project Status Initiated 04/22/2004
    Project Status Advertised 04/25/2020
    Project Management
    100% Design 100% Package Received 07/12/2019
    25% Design 25% Package Received 04/09/2018
    25% Design 25% Package Comments to DE 08/03/2018
    25% Design 25% Package Approved 10/17/2018
    25% Design Design Public Hearing 10/18/2018
    75% Design 75% Package Received 02/27/2019
    75% Design 75% Package Comments to DE 04/29/2019
    75% Design 75% Plans Approved 05/29/2019
    75% Design 75% Plans Complete 05/29/2019
    Final Design PS&E Received 12/11/2019
    Final Design PS&E to FAPRO 04/03/2020