Project Description: |
ANDOVER- LAWRENCE- NORTH ANDOVER- RESURFACING AND RELATED WORK, I-495
This project involves resurfacing I-495 from the Tewksbury town line to the Massachusetts Avenue bridge in North Andover. The project includes replacing guardrail as needed, repairing drainage structures and paved waterways and installing traffic data collection stations.
|
Location: |
|
Resident Engineer: | James Slavit |
Construction Contract Value: | $9,859,630.93 |
Construction Bid Price: | $8,179,367.54 |
Initial Construction Estimate: | $6,797,590.00 |
District: | District 4 |
|