ANDOVER- LAWRENCE- NORTH ANDOVER- RESURFACING AND RELATED WORK, I-495
This project involves resurfacing I-495 from the Tewksbury town line to the Massachusetts Avenue bridge in North Andover. The project includes replacing guardrail as needed, repairing drainage structures and paved waterways and installing traffic data collection stations.
Location:
  • Town of Andover
  • City of Lawrence
  • Town of North Andover
  • Resident Engineer: James Slavit
    Construction Contract Value: $9,859,630.93
    Construction Bid Price: $8,179,367.54
    Initial Construction Estimate: $6,797,590.00
    District: District 4

    Contracts (1) Progress
    # 41981 -- Construction Contract
    Work consist of resurfacing and related work on Route I-495 both Northbound and Southbound in the Town of Andover, City of Lawrence, and Town of North Andover. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/29/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/22/2004
    Project Review Committee Letter 08/10/2004
    Project Status Initiated 04/28/2004
    Project Status Advertised 03/26/2005
    Project Management
    100% Design 100% Package Received 03/07/2005
    75% Design 75% Plans Approved 03/07/2005
    Final Design PS&E Received 03/22/2005
    Final Design PS&E to FAPRO 03/22/2005