Project Description: |
WESTMINSTER- RESURFACING AND RELATED WORK, ROUTE 2 OVER ROUTE 140N TO EXIT 26
The westerly limit of Rte 2 in Westminster is Bridge W-28-021 over Route 140 North (mm 89.9±). The easterly limit of Rte 2 in Westminster is a pavement joint in the vicinity of Exit 26 (mm 92.4±). The total length of this project is approximately 2.5 miles.
|
Location: |
|
Resident Engineer: | Steven Toloczko |
Construction Contract Value: | $5,113,106.50 |
Construction Bid Price: | $3,827,506.50 |
Initial Construction Estimate: | $3,608,655.00 |
District: | District 3 |
Current Status: | (as of 06/19/2008) |
|
Bridges |
|
|
|
|