Project Description:
WESTMINSTER- RESURFACING AND RELATED WORK, ROUTE 2 OVER ROUTE 140N TO EXIT 26
The westerly limit of Rte 2 in Westminster is Bridge W-28-021 over Route 140 North (mm 89.9±). The easterly limit of Rte 2 in Westminster is a pavement joint in the vicinity of Exit 26 (mm 92.4±). The total length of this project is approximately 2.5 miles.
Location:
  • Town of Westminster
  • Resident Engineer: Steven Toloczko
    Construction Contract Value: $5,113,106.50
    Construction Bid Price: $3,827,506.50
    Initial Construction Estimate: $3,608,655.00
    District: District 3
    Current Status: (as of 06/19/2008)

    Contracts (1) Progress
    # 43792 -- Construction Contract
    This project consists of the resurfacing of Route 2 in Westminster. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/18/2006
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/22/2004
    Project Status Initiated 04/28/2004
    Project Status Advertised 08/20/2005
    Project Management
    Final Design PS&E Received 08/11/2005
    Final Design PS&E to FAPRO 08/11/2005