Project Description: |
WESTMINSTER- RESURFACING AND RELATED WORK, ROUTE 2 OVER ROUTE 140N TO EXIT 26
The westerly limit of Rte 2 in Westminster is Bridge W-28-021 over Route 140 North (mm 89.9±). The easterly limit of Rte 2 in Westminster is a pavement joint in the vicinity of Exit 26 (mm 92.4±). The total length of this project is approximately 2.5 miles.
|
Location: |
|
Design Responsibility: | In-House Boston |
Right of Way Responsibility: | MassDOT |
Project Manager: | Albert Li![]() |
Estimated Total Contract Cost: | $5,113,106.50 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 3 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|