Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
AGAWAM- RESIDENT WATER SUPPLY AND WELL CLOSURE, ROUTE 57
Location:
  • City of Agawam
  • Resident Engineer: Perry Knickerbocker
    Construction Contract Value: $146,373.00
    Construction Bid Price: $131,673.00
    Initial Construction Estimate: $191,465.00
    District: District 2

    Contracts (1) Progress
    # 44024 -- Construction Contract
    Agawam - Water Service Connections on Southwick Street (Route 57) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/18/2006
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/22/2004
    Project Review Committee Letter 07/06/2004
    Project Status Initiated 04/29/2004
    Project Status Advertised 11/13/2004
    Project Status Advertised 09/03/2005
    Project Management
    75% Design 75% Package Comments to DE 10/05/2004
    Final Design PS&E Received 11/05/2004
    Final Design PS&E to FAPRO 11/05/2004