Project Description:
HOLYOKE- WEST SPRINGFIELD- REHABILITATION OF ROUTE 5 (RIVERDALE ROAD), FROM I-91 (INTERCHANGE 13) TO MAIN STREET IN HOLYOKE & FROM ELM STREET TO NORTH ELM STREET IN WEST SPRINGFIELD (3.2 MILES)
The project consists of rehabilitating two sections of concrete pavement on Route 5 in Holyoke and West Springfield. The current project limits begin in West Springfield immediately to the north of the I-91 Exit 13 Interchange, and extend northerly to the intersection with Main Street in Holyoke (2.2mi) - the second section extends from East Elm Street (@McDonalds) northerly to North Elm Street near the dike (1.0mi). Total project length is 3.2 miles. The proposed work on section one will include roadway rehabilitation and new and reconstructed sidewalks and traffic signals. Section two will only include new and reconstructed sidewalks and wheelchair ramps. The project also includes modification to the intersection with Ashley Avenue to add a dedicated left turn lane. Other work includes traffic signal updates at several locations, drainage system improvements, and guardrail improvements.
Location:
  • City of Holyoke
  • Town of West Springfield
  • Construction Begins: Autumn 2023
    Resident Engineer: Guilherme Fill
    Construction Bid Price: $53,546,148.00
    District: District 2

    Contracts (4) Progress
    # 115784 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 123409 -- Construction Contract
    Rehabilitation of Route 5 (Riverdale Road), from I-91 (Interchange 13) .to Main Street in Holyoke & from Elm Street to North Elm Street in West Springfield (3.2 Miles)
    # 77860 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77867 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/05/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/22/2004
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 07/19/2004
    Project Review Committee Resubmitted 04/11/2005
    Project Status Initiated 05/10/2004
    Project Status Advertised 07/29/2023
    Project Management
    100% Design 100% Package Received 02/23/2022
    100% Design 100% Package Comments to DE 04/22/2022
    25% Design 25% Package Received 12/13/2019
    25% Design 25% Package Comments to DE 02/14/2020
    25% Design Design Public Hearing 07/15/2020
    75% Design 75% Package Received 12/21/2020
    75% Design 75% Package Comments to DE 01/06/2021
    75% Design 75% Package Received - Resub 1 05/26/2021
    Final Design PS&E Received 04/28/2023
    Final Design PS&E to Peer Reviewer 05/05/2023
    Final Design Peer Review Comments to DE 05/31/2023
    Final Design PS&E to FAPRO 05/26/2023
    Final Design PS&E Received - Resub 1 06/28/2023
    Consultant Contract Process NTP Issued 11/21/2018