WEST SPRINGFIELD- RECONSTRUCTION OF ROUTE 5 (RIVERDALE STREET) FROM I-91 TO MONTEREY DRIVE
The work on Route 5 in West Springfield consists of removing the existing concrete pavement and replacing it with asphalt pavement. New sidewalks will be constructed and intersection improvements ,including traffic signal modifications, between I-91 and Monterey Drive will be made.
Location:
  • Town of West Springfield
  • Resident Engineer: James Hurley
    Construction Contract Value: $4,300,131.00
    Construction Bid Price: $3,687,755.50
    Initial Construction Estimate: $3,655,688.00
    District: District 2

    Contracts (1) Progress
    # 66938 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Route 5 (Riverdale Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/31/2010
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Other types not listed
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/22/2004
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 07/19/2004
    Project Review Committee Resubmitted 04/11/2005
    Project Status Initiated 05/10/2004
    Project Status Advertised 08/07/2010
    Project Management
    100% Design 100% Package Received 06/11/2010
    100% Design 100% Package Comments to DE 06/30/2010
    100% Design 100% Plans Approved 06/30/2010
    25% Design 25% Package Received 08/28/2009
    25% Design 25% Package Comments to DE 10/23/2009
    25% Design Design Public Hearing 12/22/2009
    75% Design 75% Package Received 03/05/2010
    75% Design 75% Package Comments to DE 04/15/2010
    Final Design PS&E Received 07/02/2010
    Final Design PS&E to FAPRO 08/03/2010