Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NORTHAMPTON- MANHAN/NORWOTTUCK TRAIL CONSTRUCTION, INCLUDING EARLE STREET/GROVE STREET INTERSECTION TO NEW SOUTH STREET, INCLUDES BR# N-19-072
This rail trail project starts at the former Northampton State Hospital and includes the Earle Street/Grove Street intersection and continues to the New South Street in downtown Northampton, for a total distance of .07 Miles.
Location:
  • City of Northampton
  • Resident Engineer: Eric Grady
    Construction Contract Value: $2,621,324.71
    Construction Bid Price: $1,494,538.00
    Initial Construction Estimate: $1,296,369.30
    District: District 2
    Current Status: Project under construction (as of 03/26/2008)
    Additional Info: Daily lane rstrictions/reductions during the work week. All lanes open at end of the work day and weekends. (as of 03/26/2008)

    Contracts (1) Progress
    # 52343 -- Construction Contract
    Northampton - Construction of Manhan Rail Trail Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/06/2007
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project under construction
    Additional Info
    Daily lane rstrictions/reductions during the work week. All lanes open at end of the work day and weekends.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/22/2004
    Project Review Committee Letter 07/06/2004
    Project Status Initiated 06/07/2004
    Project Status Advertised 06/24/2006
    Project Management
    100% Design 100% Package Received 06/30/2005
    100% Design 100% Package Received 09/22/2005
    100% Design 100% Package Comments to DE 11/04/2005
    25% Design Design Public Hearing 11/30/1999
    75% Design 75% Package Received 06/03/2005
    Final Design PS&E Received 03/24/2006
    Final Design PS&E to FAPRO 04/25/2006