Project Description:
NORTHFIELD- SCENIC BYWAY CONSTRUCTION ON ROUTE 10/63 (PHASE I)
The focus of the Northfield Street Improvement Project is to reconstruct sidewalks on Main Street and Parker Avenue in Northfield from a point north of the intersection with River Street continuing northerly for approximately 1.77 miles, and ending at the intersection with Moody Street. The work also includes improving safety at the Parker Ave. intersection, repairing sidewalks on several adjacent roadways, restoring the town common, enhancing surrounding areas, and addressing traffic and pedestrian safety concerns. The project will incorporate sidewalk and streetscape elements to restore historic town character and continue work initiated under the DEM Town Commons Preservation Project completed in 2000.
Location:
  • Town of Northfield
  • Resident Engineer: John Burek
    Construction Contract Value: $970,866.00
    Construction Bid Price: $874,424.00
    Initial Construction Estimate: $1,398,869.00
    District: District 2

    Contracts (1) Progress
    # 58282 -- Construction Contract
    Sidewalk Reconstruction and Related Work on a Section of Route 10 & 63 (Main Street) (Scenic Byway Construction - Phase I). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/07/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/22/2004
    Project Review Committee Letter 07/19/2004
    Project Status Initiated 06/10/2004
    Project Status Advertised 03/21/2009
    Project Management
    100% Design 100% Package Received 12/08/2008
    100% Design 100% Package Comments to DE 01/09/2009
    25% Design 25% Package Received 03/04/2008
    25% Design 25% Package Comments to DE 05/12/2008
    25% Design Design Public Hearing 10/03/2007
    75% Design 75% Package Received 10/03/2008
    Final Design PS&E Received 02/24/2009
    Final Design PS&E to FAPRO 03/18/2009