WHATELY- PARK & RIDE CONSTRUCTION AT THE ROUTE 116, ROUTE 5&10 INTERSECTION
The proposed project consists of providing approximately 55 parking spaces along with bicycle racks, pedestrian walks, and a bus stop with shelter. It will be located adjacent to the intersection of Route 116 with Greenfield Road (Routes 5 and 10).
Location:
  • Town of Whately
  • Resident Engineer: Mark Joy
    Construction Contract Value: $1,177,984.00
    Construction Bid Price: $1,066,195.00
    Initial Construction Estimate: $1,271,849.00
    District: District 2

    Contracts (4) Progress
    # 51194 -- Design -- Highway
    Work includes design for two park and ride lots with associated amenities - one in Northampton and the second in Whately. Final
    # 64304 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70966 -- Construction Contract
    Constriction of a Park and Ride Lot at the Intersection of Routes 5/10 and 116. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/16/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/22/2004
    Project Review Committee Letter 07/23/2004
    Project Status Initiated 06/15/2004
    Project Status Advertised 09/10/2011
    Project Management
    100% Design 100% Package Received 03/04/2011
    100% Design 100% Package Comments to DE 05/13/2011
    25% Design 25% Package Received 05/06/2009
    25% Design 25% Package Comments to DE 11/09/2009
    25% Design Design Public Hearing 07/28/2010
    75% Design 75% Package Received 03/04/2011
    75% Design 75% Package Comments to DE 05/13/2011
    Final Design PS&E Received 06/27/2011
    Final Design PS&E to FAPRO 09/07/2011
    Consultant Contract Process Scope to DE 02/19/2008