Project Description:
BOURNE- COLD PLANING AND RESURFACING ON ROUTE 6 (SCENIC HIGHWAY)
The purpose of this project is to resurface the Bourne Route 6 Scenic Highway from the intersection with Nightingale Pond Road to just east of the intersection with Bourndale Road.
Location:
  • Town of Bourne
  • Resident Engineer: Daniel Mastrangelo
    Construction Contract Value: $1,651,519.00
    Construction Bid Price: $1,419,967.50
    Initial Construction Estimate: $1,459,612.00
    District: District 5

    Contracts (1) Progress
    # 58179 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 6 (Scenic Highway). (ARRA Project) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/23/2009
    Contract Information
    Project Designer: In-House Boston
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/22/2004
    Project Review Committee Letter 08/06/2004
    Project Status Initiated 06/16/2004
    Project Status Advertised 03/14/2009
    Project Management
    Final Design PS&E Received 09/18/2008
    Final Design PS&E to FAPRO 02/24/2009