CHARLTON- STURBRIDGE- RESURFACING AND RELATED WORK, ROUTE 20, FROM THE JUNCTION OF ROUTE 169 TO THE JUNCTION OF ROUTE 49
This project involves resurfacing, guardrail replacement, drainage system cleaning and repairs, and tree & brush removal along the shoulder of Route 20. This project begins at the junction of Route 169 in Charlton and continues westerly 3.2 miles to the junction of Route 49 in Sturbridge.
Location:
  • Town of Charlton
  • Town of Sturbridge
  • Resident Engineer: Paul Thompson
    Construction Contract Value: $2,837,310.04
    Construction Bid Price: $2,290,158.00
    Initial Construction Estimate: $2,403,081.00
    District: District 3

    Contracts (1) Progress
    # 43272 -- Construction Contract
    Project consists of the resurfacing of Route 20 in Charlton and Sturbridge. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/10/2006
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 06/21/2004
    Project Status Advertised 07/09/2005
    Project Status Advertised 08/06/2005
    Project Management
    100% Design 100% Plans Complete 07/07/2005
    Final Design PS&E Received 07/29/2005
    Final Design PS&E to FAPRO 07/29/2005