Project Description:
AUBURN- OXFORD- RECONSTRUCTION & IMPROVEMENTS ON ROUTE 12/20 OVERLAP, FROM THE ROUTE 12/20 INTERSECTION (OXFORD) TO ROUTE 12/20 INTERSECTION (AUBURN)
The proposed improvements provide a raised median to separate eastbound and westbound vehicles and wider outside travel lanes along the project length. The raised median and increased outside lane width will provide improved definition for this corridor. Dividing the roadway will eliminate lefts turns and minimize cross-over accidents. An effort will be made to consolidate curb cuts along this congested section of roadway.
Location:
  • Town of Auburn
  • Town of Oxford
  • Resident Engineer: Jean-Pierre Telemaque
    Construction Contract Value: $8,717,489.00
    Construction Bid Price: $6,594,408.25
    Initial Construction Estimate: $6,181,887.50
    District: District 3

    Contracts (3) Progress
    # 54138 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 75585 -- Construction Contract
    Roadway Reconstruction and Related Work on Sections of Main, Southbridge and Washington Streets (Route 12 and 20). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/20/2013
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/22/2004
    Project Status Initiated 06/21/2004
    Project Status Advertised 09/15/2012
    Project Management
    100% Design 100% Package Received 06/06/2012
    100% Design 100% Package Comments to DE 08/24/2012
    25% Design 25% Package Received 03/29/2010
    25% Design 25% Package Comments to DE 07/18/2011
    25% Design Design Public Hearing 03/08/2011
    75% Design 75% Package Received 03/06/2012
    75% Design 75% Package Comments to DE 05/10/2012
    Final Design PS&E Received 09/10/2012
    Final Design PS&E to FAPRO 09/11/2012