DISTRICT 4- NON-ROUTINE MAINTENANCE AND EMERGENCY BRIDGE REPAIRS (CONTRACT #1)
Location:
Resident Engineer: Robert Huettner
Construction Contract Value: $3,090,510.00
Construction Bid Price: $834,510.00
Initial Construction Estimate: $774,000.00
District: District 4
Current Status: Work under this contract consists of preparing structural repair designs and furnishing various artisans- iron workers, mechanics, welders, carpenters, laborers-- and materials , supplies ,equipment and engineering services to perform non-routine and emergency services and emergency structural repairs. (as of 11/01/2007)
Additional Info: Work locations for Sept 2007 Woburn- Salem St. over the MBTA Billerica- River St. over the Concord River. Newton- Rte 9 @ Chestnut St. and Rte 9 @ pedestrian bridge. (as of 11/01/2007)

Contracts (1) Progress
# 41210 -- Construction Contract
Bridge Repairs at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/13/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Initiated 06/23/2004
    Project Status Advertised 12/11/2004
    Project Management
    Final Design PS&E Received 12/08/2004