| Project Description:
|
DISTRICT 4- NON-ROUTINE MAINTENANCE AND EMERGENCY BRIDGE REPAIRS (CONTRACT #1)
|
| Location:
|
|
| Resident Engineer:
|
Robert Huettner |
| Construction Contract Value:
|
$3,090,510.00 |
| Construction Bid Price:
|
$834,510.00 |
| Initial Construction Estimate:
|
$774,000.00 |
| District:
|
District 4 |
| Current Status:
|
Work under this contract consists of preparing structural repair designs and furnishing various artisans- iron workers, mechanics, welders, carpenters, laborers-- and materials , supplies ,equipment and engineering services to perform non-routine and emergency services and emergency structural repairs. (as of 11/01/2007) |
| Additional Info:
|
Work locations for Sept 2007
Woburn- Salem St. over the MBTA
Billerica- River St. over the Concord River.
Newton- Rte 9 @ Chestnut St. and Rte 9 @ pedestrian bridge.
(as of 11/01/2007) |