Project Description:
MILLIS- BRIDGE REPLACEMENT, M-23-005, ROUTE 115 (NORFOLK ROAD) OVER THE CHARLES RIVER
This project will replace the existing bridge deck with with a new scour protected substructure, which will widen the existing roadway width from 30 feet to 32 feet, maintaining the existing two lane cross-section. The proposed bridge will widen the existing sidewalk and incorporate a utility bay. Existing traffic patterns will be maintained during construction.
Location:
  • Town of Millis
  • Resident Engineer: Julio Fontecchio
    Construction Contract Value: $1,557,689.00
    Construction Bid Price: $1,364,809.00
    Initial Construction Estimate: $1,841,365.00
    District: District 3

    Contracts (4) Progress
    # 34492 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 5 - Contract C Final
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 57728 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 60374 -- Construction Contract
    Bridge Replacement (M-23-005) (Concrete) - Route 115 (Norfolk Road) over the Charles River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/28/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 06/25/2004
    Project Status Advertised 08/29/2009
    Project Management
    100% Design 100% Package Received 06/11/2008
    100% Design 100% Package Comments to DE 09/26/2008
    25% Design 25% Package Received 06/08/2005
    25% Design 25% Package Comments to DE 09/16/2005
    75% Design 75% Package Received 09/19/2006
    Final Design PS&E Received 08/07/2009
    Final Design PS&E to FAPRO 08/26/2009