Project Description: |
MILLIS- BRIDGE REPLACEMENT, M-23-005, ROUTE 115 (NORFOLK ROAD) OVER THE CHARLES RIVER
This project will replace the existing bridge deck with with a new scour protected substructure, which will widen the existing roadway width from 30 feet to 32 feet, maintaining the existing two lane cross-section. The proposed bridge will widen the existing sidewalk and incorporate a utility bay. Existing traffic patterns will be maintained during construction.
|
Location: |
|
Resident Engineer: | Julio Fontecchio |
Construction Contract Value: | $1,557,689.00 |
Construction Bid Price: | $1,364,809.00 |
Initial Construction Estimate: | $1,841,365.00 |
District: | District 3 |
|