Project Description:
NORTHAMPTON- BRIDGE REPLACEMENT, N-19-035, KENNEDY ROAD OVER ROBERTS MEADOW BROOK
The proposed work includes replacing the bridge carrying Kennedy Road over Roberts Meadow Brook in Northampton. The existing city-owned bridge, constructed in 1925 and reconstructed in 1955, is a single span steel stringer structure with a reinforced concrete deck on corrugated galvanized steel forms with a curb to curb width of 16.0 feet and no sidewalk. The proposed bridge width is 24.0 feet curb to curb and no sidewalks. The existing structure will be closed to traffic during construction, and a detour will be in place.
Location:
  • City of Northampton
  • Resident Engineer: David Virgilio
    Construction Contract Value: $725,727.00
    Construction Bid Price: $647,025.00
    Initial Construction Estimate: $840,040.00
    District: District 2

    Contracts (4) Progress
    # 34494 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 5 - Contract E Final
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 72203 -- Construction Contract
    Bridge Replacement (N-19-035) (Concrete) - Kennedy Road over Roberts Meadow Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/15/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Status Initiated 07/15/2004
    Project Status Advertised 12/17/2011
    Project Management
    100% Design 100% Package Received 09/28/2011
    100% Design 100% Package Comments to DE 10/26/2011
    25% Design 25% Package Received 02/25/2009
    25% Design 25% Package Comments to DE 04/14/2011
    25% Design 25% Package Comments to DE 06/15/2011
    25% Design Design Public Hearing 03/09/2011
    75% Design 75% Package Received 07/25/2011
    75% Design 75% Package Comments to DE 08/16/2011
    Final Design PS&E Received 11/21/2011
    Final Design PS&E to FAPRO 12/14/2011
    Consultant Contract Process Scope to DE 11/02/2004
    Consultant Contract Process NTP Issued 01/27/2005