WHATELY- BRIDGE REPLACEMENT, W-33-009, HAYDENVILLE ROAD OVER WEST BROOK
The proposed work includes replacing the Haydenville Road bridge over West Brook in Whately. The existing town-owned bridge, constructed in 1880 and reconstructed in 1951, is a single span steel stringer structure with a curb to curb width of 27 feet, 9 inches and no sidewalks. The proposed bridge width is 28 feet 10 inches curb to curb. The bridge is to be constructed in stages to allow one lane of traffic at all times with traffic signals.
Location:
  • Town of Whately
  • Resident Engineer: David Virgilio
    Construction Contract Value: $1,192,664.00
    Construction Bid Price: $1,021,294.85
    Initial Construction Estimate: $1,364,490.50
    District: District 2

    Contracts (1) Progress
    # 62909 -- Construction Contract
    Bridge Replacement (W-33-009) (Concrete) - Haydenville Road over West Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/20/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Status Initiated 07/15/2004
    Project Status Advertised 12/12/2009
    Project Management
    100% Design 100% Package Received 03/23/2009
    100% Design 100% Package Comments to DE 05/06/2009
    25% Design 25% Package Received 01/31/2008
    25% Design Design Public Hearing 05/28/2008
    75% Design 75% Package Received 08/27/2008
    75% Design 75% Package Comments to DE 11/25/2008
    Final Design PS&E Received 10/06/2009
    Final Design PS&E to FAPRO 10/13/2009
    Consultant Contract Process Scope to DE 03/14/2005
    Consultant Contract Process NTP Issued 09/15/2005