Project Description:
GREAT BARRINGTON- TRAFFIC SIGNAL INSTALLATION, ROUTE 7 AT MONUMENT VALLEY ROAD
The work consists of traffic signal installation at the intersection of Route 7 with Monument Valley Road. The installation includes mast arms, traffic signals, wire loop detectors, traffic controller and all miscellaneous wire, conduit, and cable.
Location:
  • Town of Great Barrington
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: Other
    Project Manager: Ranjit Sivasubramaniam
    Estimated Total Federal Participating Construction Cost: $180,435.00
    District: District 1
    Current Status: This project has been advertised for construction bids. (as of 09/18/2004 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Initiated 09/04/2004
    Project Status Advertised 09/18/2004
    Project Management
    Final Design PS&E Received 09/10/2004
    Final Design PS&E to FAPRO 09/10/2004