Project Description:
SUTTON- BRIDGE RECONSTRUCTION, S-33-013, MAIN STREET OVER THE MUMFORD RIVER
The existing structure consists of a single span steel stringer bridge that is structurally deficient and is scheduled to be replaced in the same location with a new single span steel stringer bridge. The proposed bridge will be similar to the existing bridge and will retain essentially the same horizontal alignment and vertical profile. The proposed bridge will accommodate two travel lanes for vehicular traffic with sidewalks on both sides for pedestrian traffic. The work will be staged to maintain vehicular and pedestrian access during construction.
Location:
  • Town of Sutton
  • Resident Engineer: Stephen Shamoian
    Construction Contract Value: $1,209,183.10
    Construction Bid Price: $1,020,362.55
    Initial Construction Estimate: $1,361,581.00
    District: District 3

    Contracts (6) Progress
    # 34493 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 5 - Contract D Final
    # 43179 -- Design -- Hwy Eng Open End
    Layout Section requires a consultant to provide the service of Layout plan and written description preparation. Final
    # 54837 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57464 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 57465 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 65279 -- Construction Contract
    Bridge Reconstruction (S-33-013) (Steel) - Main Street over the Mumford River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/12/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 07/19/2004
    Project Status Advertised 06/12/2010
    Project Management
    25% Design 25% Package Received 09/05/2006
    25% Design 25% Package Comments to DE 10/29/2007
    25% Design Design Public Hearing 04/22/2009
    75% Design 75% Package Received 08/10/2009
    75% Design 75% Package Comments to DE 11/04/2009
    Final Design PS&E Received 03/08/2010
    Final Design PS&E Received 05/26/2010
    Final Design PS&E to FAPRO 06/09/2010
    Consultant Contract Process Scope to DE 11/10/2004
    Consultant Contract Process NTP Issued 07/11/2008
    Consultant Contract Process Workhours Approved 07/29/2005