Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
OTIS- BRIDGE REHABILITATION, O-05-005, RESERVOIR ROAD OVER THE WEST BRANCH OF THE FARMINGTON RIVER
The proposed work will replace the bridge superstructure, modify the existing abutments and wingwalls, reconstruct the roadway at the approaches and improve safety by adding guardrail transitions, pavement markings and signing.
Location:
  • Town of Otis
  • Resident Engineer: Hugo Pacheco
    Construction Contract Value: $837,973.00
    Construction Bid Price: $749,521.44
    Initial Construction Estimate: $1,060,029.00
    District: District 1

    Contracts (3) Progress
    # 30272 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 58594 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 67667 -- Construction Contract
    Bridge Superstructure Replacement (O-05-005) (Concrete) – Reservoir Road over the West Branch of the Farmington River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/10/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 02/27/2006
    Project Status Initiated 08/17/2004
    Project Status Advertised 09/11/2010
    Project Management
    100% Design 100% Package Received 08/17/2010
    100% Design 100% Package Comments to DE 06/25/2010
    25% Design 25% Package Received 01/25/2006
    25% Design 25% Package Comments to DE 04/21/2010
    25% Design 25% Package Comments to DE 04/23/2010
    25% Design Design Public Hearing 06/29/2006
    25% Design Design Public Hearing 03/16/2009
    75% Design 75% Package Received 06/29/2009
    75% Design 75% Package Comments to DE 08/24/2009
    Final Design PS&E Received 09/07/2010
    Final Design PS&E to FAPRO 09/07/2010
    Consultant Contract Process Scope to DE 11/15/2004
    Consultant Contract Process NTP Issued 03/02/2005
    Consultant Contract Process Workhours Approved 02/28/2005