Project Description:
BUCKLAND- RECONSTRUCTION OF STATE STREET, FROM CLEMENT STREET TO ROUTE 2
The project begins at Clement Street in Buckland and ends at Route 2, a distance of 4000 feet. The project includes milling and removal of existing asphalt down to the binder course or concrete pavement where still present. Joints in the underlying concrete pavement will be repaired as needed. Drainage will be upgraded and curbing will be reset or replaced with granite. Adjacent sidewalks will be reconstructed to ADA compliance. New pavement markings will be applied and guard rail and signs will be updated. The Town has also proposed to do water and sewer system repairs during construction.
Location:
  • Town of Buckland
  • Resident Engineer: Russell Duval
    Construction Contract Value: $2,179,308.00
    Construction Bid Price: $2,398,217.00
    Initial Construction Estimate: $3,118,499.70
    District: District 1

    Contracts (1) Progress
    # 66837 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of State Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/10/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 11/03/2005
    Project Status Advertised 07/31/2010
    Project Management
    100% Design 100% Package Received 03/23/2010
    100% Design 100% Package Comments to DE 05/11/2010
    25% Design 25% Package Received 03/04/2009
    25% Design 25% Package Comments to DE 06/02/2009
    25% Design 25% Package Approved 09/29/2009
    25% Design Design Public Hearing 08/17/2009
    75% Design 75% Package Received 11/09/2009
    75% Design 75% Package Comments to DE 01/08/2010
    Final Design PS&E Received 06/08/2010
    Final Design PS&E to FAPRO 07/27/2010