Project Description: |
BOURNE- SAGAMORE ROTARY LANDSCAPING CONTRACT
The purpose of the Bourne Interchange Landscape project is to re-establish patches of native woodland on land opened up by the imminent construction of the new Route 3 Interchange. The design of the native woodland is based on the scrub oak/ pine indigenous to the Cape Cod sand plain community and incorporates a combination of pitch pine, red oak, black oak, red maple, gray birch and shade trees.
|
Location: |
|
Resident Engineer: | Daniel Mastrangelo |
Construction Contract Value: | $1,654,147.00 |
Construction Bid Price: | $1,482,679.50 |
Initial Construction Estimate: | $1,691,160.00 |
District: | District 5 |
|
Bridges |
|
|
|
|