Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NANTUCKET- BIKE PATH CONSTRUCTION ON CLIFF ROAD
The proposed project consists of the construction of a 0.5 mile shared pathway which runs parallel along the roadway between the intersection of Crooked Lane and Sherburne Turnpike. The roadway and the pathway will be separated by a grass strip and curbing to provide a physical barrier. The pathway crosses Gosnold Road, Hinckley Lane, Shady Lane and several driveways.
Location:
  • Town of Nantucket
  • Resident Engineer: Thomas Ockerbloom
    Construction Contract Value: $768,696.00
    Construction Bid Price: $690,633.00
    Initial Construction Estimate: $747,430.00
    District: District 5

    Contracts (1) Progress
    # 66677 -- Construction Contract
    Construction of Cliff Road Bicycle Path Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/04/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 09/14/2006
    Project Review Committee Letter 10/04/2006
    Project Status Initiated 08/28/2006
    Project Status Advertised 08/14/2010
    Project Management
    100% Design 100% Package Received 12/28/2009
    100% Design 100% Package Comments to DE 03/15/2010
    25% Design 25% Package Received 08/06/2008
    25% Design 25% Package Comments to DE 07/16/2007
    25% Design Design Public Hearing 12/16/2008
    75% Design 75% Package Received 09/10/2009
    75% Design 75% Package Comments to DE 11/09/2009
    Final Design PS&E Received 06/10/2010
    Final Design PS&E to FAPRO 08/11/2010
    Consultant Contract Process Scope to DE 11/15/2005
    Consultant Contract Process NTP Issued 02/08/2006