Project Description: |
SOMERSET- SWANSEA- INTERSTATE RESURFACING ON I-195
The project includes repaving, safety improvements and bridge rehabilitation on the Interstate system. The project begins at the Rehoboth/Swansea line and ends just west of the Braga Bridge for a total project length of 6.7 miles.
|
Location: |
|
Resident Engineer: | Daniel Vieira |
Construction Contract Value: | $10,949,667.66 |
Construction Bid Price: | $8,634,999.00 |
Initial Construction Estimate: | $9,378,447.00 |
District: | District 5 |
|