Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 5- COLD PLANING AND RESURFACING AT VARIOUS LOCATIONS (AREA D)
Location:
Resident Engineer: Malcolm Lavalley
Construction Contract Value: $1,342,170.00
Construction Bid Price: $1,210,970.00
Initial Construction Estimate: $1,015,790.00
District: District 5

Contracts (1) Progress
# 54893 -- Construction Contract
Works including cold planing and resurfacing at various locations in Area D (Brewster, Dennis, Harwich, Truro and Yarmouth) Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/26/2008
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 04/25/2005
    Project Status Initiated 09/23/2004
    Project Status Advertised 03/01/2008
    Project Management
    100% Design 100% Package Received 04/27/2007
    75% Design 75% Plans Complete 04/27/2007
    Final Design PS&E Received 05/23/2007
    Final Design PS&E to FAPRO 05/25/2007