DISTRICT 5- SIDEWALK REPAIR AT VARIOUS LOCATIONS IN AREA B
Location:
Resident Engineer: Gregory Nicholas
Construction Contract Value: $595,704.00
Construction Bid Price: $426,800.00
Initial Construction Estimate: $363,825.00
District: District 5

Contracts (1) Progress
# 42244 -- Construction Contract
Work consist of new installation and the repair of asphalt and cement concrete sidewalk areas in AREA B at various locations as determined by the Engineer. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/29/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 04/25/2005
    Project Status Initiated 09/28/2004
    Project Status Advertised 05/14/2005
    Project Management
    Final Design PS&E Received 03/01/2005
    Final Design PS&E to FAPRO 05/09/2005