FAIRHAVEN- NEW BEDFORD- BRIDGE PRESERVATION, F-01-002=N-06-001 (EAST & WEST BRIDGES) ROUTE 6 OVER ACUSHNET RIVER & N-06-025, HATHAWAY ROAD OVER ROUTE I-195
The purpose of this project is to increase the lifespan of two bridges in Fairhaven and New Bedford through maintenance. The work includes replacing joints, replacing bearings, cleaning and repairing steel, and repairing concrete and granite piers and abutments for both west and east bridges on Route 6 over the Acushnet River.
Location:
  • Town of Fairhaven
  • City of New Bedford
  • Resident Engineer: Emanuel Aguiar
    Construction Contract Value: $21,206,568.00
    Construction Bid Price: $17,661,712.00
    Initial Construction Estimate: $22,671,084.00
    District: District 5

    Contracts (6) Progress
    # 54832 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 54835 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 58595 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 68152 -- Construction Contract
    FAIRHAVEN-NEW BEDFORD - 2 Bridge Reconstructions (Including Painting) (F-01-002=N-06-001) (Steel) - Route 6 EB & WB over the Acushnet River and Bridge (N-06-025) (Steel) - Hat Completed
    # 71613 -- Design -- Bridge Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for bridge, traffic and utility permit structural design and analysis assignments. Final
    # 77862 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/29/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 10/06/2004
    Project Status Advertised 05/14/2005
    Project Status Advertised 09/25/2010
    Project Status Advertised 02/19/2011
    Project Management
    100% Design 100% Package Received 07/30/2010
    100% Design 100% Package Comments to DE 08/30/2010
    25% Design 25% Package Received 04/23/2010
    25% Design 25% Package Comments to DE 06/11/2010
    25% Design Design Public Hearing 06/24/2010
    Final Design PS&E Received 09/15/2010
    Final Design PS&E Received 09/15/2010
    Final Design PS&E to FAPRO 09/21/2010
    Consultant Contract Process NTP Issued 02/12/2010
    Consultant Contract Process Workhours Approved 01/29/2010