SANDWICH- RECONSTRUCTION OF ROUTE 130, WATER STREET @ MAIN STREET
The proposed project will consist of minor geometric alterations; cold plane and overlay of the existing pavement; installation of new granite curb and edging; construction of asphalt sidewalks and concrete wheelchair ramps; tree and shrub plantings; installation of new signage and pavement markings as well as improvements to the existing roadway drainage system.
Location:
  • Town of Sandwich
  • Resident Engineer: Daniel Mastrangelo
    Construction Contract Value: $646,319.00
    Construction Bid Price: $546,656.65
    Initial Construction Estimate: $578,324.00
    District: District 5

    Contracts (1) Progress
    # 53362 -- Construction Contract
    Sandwich - Intersection Reconstruction and Related Work at Route 130 (Water Street) and Main Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/14/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 10/25/2004
    Project Status Advertised 09/23/2006
    Project Management
    100% Design 100% Package Received 09/19/2006
    100% Design 100% Package Comments to DE 11/30/2006
    25% Design 25% Package Received 07/01/2004
    25% Design 25% Package Received 09/01/2005
    25% Design 25% Package Received 11/01/2005
    25% Design 25% Package Received 11/21/2005
    25% Design 25% Package Received 01/31/2006
    25% Design 25% Package Comments to DE 10/20/2005
    25% Design 25% Package Comments to DE 11/21/2005
    25% Design 25% Package Comments to DE 02/17/2006
    25% Design Design Public Hearing 11/21/2005
    75% Design 75% Package Received 06/12/2006
    75% Design 75% Package Comments to DE 07/31/2006
    75% Design 75% Plans Approved 09/12/2006
    Final Design PS&E Received 09/21/2006
    Final Design PS&E Received 01/17/2007
    Final Design PS&E to FAPRO 09/20/2006